Project Type: Cleanroom
Size: 1700m²
Duration: 24 weeks
Value: £400,000
Scope of work:
IRIS was engaged through direct negotiation as a specialist contractor for this world leader in phosphor and scintillators for the detection of X-rays, neutrons, gamma rays, alpha and beta particles, UV, Visible and Infra-red radiation.
Operating as the Principal Contractor and Designer, IRIS lead a team of specialist sub-contractors and suppliers, many recruited locally, to fully validate all aspects of the facility to achieve ISO6.
IRIS’s in-house management team delivered the project to the clients brief on time and accident-free.
Reconfiguring the existing build to accommodate the clients new process requirements